FingerMotion Advances 99MW Alberta Data Center Program
TLDR
- FingerMotion is developing 99 megawatts across ten Alberta sites, positioning itself to secure lucrative AI and HPC take-or-pay contracts.
- FingerMotion's Alberta program advances ten 9.9-megawatt behind-the-meter sites, with permitting targeted by Q1 2027 and energization starting late 2026.
- FingerMotion's Alberta data center program could expand digital infrastructure for AI, potentially benefiting communities and advancing technology access.
- FingerMotion is building ten 9.9-megawatt data halls in Alberta, each powered by behind-the-meter generation and leased to AI customers.
Impact - Why it Matters
This news matters because it signals FingerMotion's strategic entry into the booming AI and high-performance computing infrastructure market, leveraging Alberta's energy resources to build behind-the-meter data centers. As AI demand for compute capacity surges, FingerMotion's plan to secure take-or-pay agreements before construction mitigates financial risk while positioning the company to capitalize on long-term contracts. The development could drive significant revenue growth and diversify FingerMotion beyond its Chinese mobile payment core, potentially enhancing shareholder value. Moreover, the project's phased approach and expansion potential demonstrate a scalable model that could be replicated, making FingerMotion a notable player in the sustainable data center space.
Summary
FingerMotion (NASDAQ: FNGR) is making significant strides in its Alberta power and compute development program, updating investors on its plans to develop ten 9.9-megawatt behind-the-meter generation and data hall sites across four campuses in Brooks, Coronation, Fox Creek, and Vulcan. These sites collectively represent 99 megawatts of gross generation capacity and approximately 72 megawatts of aggregate continuous critical IT capacity. FingerMotion holds full ownership of each project company, which in turn holds title to the land, permits, and site agreements, while BlueFlare Group Holdings Inc. handles development, construction, and site operations without holding any title to the assets.
The company is targeting completion of permitting for all 10 sites by the end of Q1 2027, with site energization expected to begin in late Q4 2026 and data hall turnover approximately 18 months after permit award. FingerMotion plans to secure long-term take-or-pay agreements with AI and high-performance computing customers before committing construction capital to individual sites. Additionally, the company intends to begin permitting an additional 15 9.9-megawatt sites in Q1 2027, expanding its campuses as customer demand requires. FingerMotion will provide the power and physical data center infrastructure, while customers supply their own GPUs, servers, network equipment, transport, and platform software. To view the full press release, visit https://ibn.fm/GG5tK.
FingerMotion is an evolving technology company with a core competency in mobile payment and recharge platform solutions in China. As its user base grows, the company is developing additional value-added technologies to market to its users. The vision is to rapidly grow the user base organically and develop an ecosystem of highly engaged users utilizing its innovative applications, strategically positioning the company to onboard larger customer bases. FingerMotion eventually hopes to serve over 1 billion users in the China market and expand the model to other regional markets. The latest news and updates relating to FNGR are available in the company’s newsroom at https://ibn.fm/FNGR. TechMediaWire, a specialized communications platform focused on pioneering public and private companies driving the future of technology, is one of 75+ brands within the Dynamic Brand Portfolio @ IBN that delivers access to a vast network of wire solutions via InvestorWire, article and editorial syndication to 5,000+ outlets, enhanced press release enhancement, social media distribution, and tailored corporate communications solutions. To receive SMS alerts from TechMediaWire, text “TECH” to 888-902-4192 (U.S. Mobile Phones Only).
Source Statement