Blue Lagoon Commissions Water Treatment, Starts Mining Sept 24 at Dome Mountain

TLDR

  • Blue Lagoon Resources gains operational advantage with its new MBBR water treatment system, enabling efficient mining scale-up to 150 tonnes per day while maintaining regulatory compliance.
  • The MBBR system at Dome Mountain treats up to 400 L/min using biofilm technology, developed with SRK Consulting to meet all discharge standards and permit conditions.
  • Blue Lagoon's environmental stewardship ensures responsible mining with full waste containment underground, protecting local ecosystems and setting a standard for sustainable resource development.
  • Blue Lagoon's Dome Mountain project is one of only nine permitted in BC since 2015, featuring advanced water treatment and underground mining commencing September 24, 2025.

Impact - Why it Matters

This development matters because it represents a rare permitted mining project in British Columbia, one of only nine approved since 2015, indicating both regulatory scrutiny and potential economic significance. The commissioning of advanced water treatment technology demonstrates evolving industry standards for environmental protection in mining operations, which is crucial given increasing public and regulatory focus on sustainable resource extraction. For investors, the transition to production phase offers potential for near-term cash flow generation, while the company's approach to keeping all waste underground and implementing robust safety protocols addresses common concerns about mining impacts. The project's progress also contributes to local economic development in the region while testing the viability of proceeding without a full feasibility study, which could influence future mining development approaches.

Summary

Blue Lagoon Resources Inc. (CSE: BLLG; OTCQB: BLAGF; FSE: 7BL) has reached a significant milestone with the commissioning readiness of its Moving Bed Biofilm Reactor (MBBR) system at the Dome Mountain Water Treatment Plant. Developed in collaboration with principal environmental consultant Soren Jensen from SRK Consulting, who brings over 20 years of expertise in mine water treatment systems, this state-of-the-art facility is designed to treat up to 400 liters per minute while current output is only 20-40 L/min, ensuring ample capacity for future scaling. The system meets all regulatory discharge standards and underscores the company's commitment to environmental stewardship as it prepares for underground mining operations.

The company has announced that underground mining will commence on September 24, 2025, beginning with development work and targeting a ramp-up to 100 tonnes per day within four weeks and 150 tpd within twelve weeks. Operational leadership is provided by Mike McCartin, an experienced underground mining geologist, supported by Roughstock Mining Services for establishing mining protocols and standard operating procedures. A key safety enhancement includes a Mutual Aid Agreement with New Gold Inc. for emergency support, while all mine waste will remain underground, further demonstrating environmental responsibility.

President & CEO Rana Vig emphasized that Dome Mountain represents one of only nine projects permitted in British Columbia since 2015, positioning Blue Lagoon for near-term cash flow generation with minimized risk. The project benefits from existing mining infrastructure and established mineral resources, though the company acknowledges increased uncertainty by proceeding without a feasibility study. This transformational phase marks the company's progression toward becoming a cash-flowing mining operation while maintaining safety and environmental care as top priorities.

Source Statement